{"record_type":"pith_number_record","schema_url":"https://pith.science/schemas/pith-number/v1.json","pith_number":"pith:2026:TX3AYJBJDFQ4CB45ZPOTLYQBZ4","short_pith_number":"pith:TX3AYJBJ","schema_version":"1.0","canonical_sha256":"9df60c24291961c1079dcbdd35e201cf1f4a4d257215b9c52753d3446c59e7e1","source":{"kind":"arxiv","id":"2605.17608","version":1},"attestation_state":"computed","paper":{"title":"Bayesian-Monte Carlo Schedule Updating for Construction Digital Twins: A Probabilistic Framework for Dynamic Project Forecasting","license":"http://arxiv.org/licenses/nonexclusive-distrib/1.0/","headline":"A Bayesian-Monte Carlo framework updates construction schedules by recursively incorporating new observations to produce adaptive probabilistic forecasts.","cross_cats":["cs.AI"],"primary_cat":"cs.CE","authors_text":"Atena Khoshkonesh, Mohsen Mohammadagha, Navid Ebrahimi, Vinayak Kaushal","submitted_at":"2026-05-17T19:09:37Z","abstract_excerpt":"Construction projects frequently experience schedule delays and forecasting uncertainty due to variability in labor productivity, material availability, weather conditions, and project coordination. Conventional deterministic scheduling methods such as the Critical Path Method (CPM) assume fixed activity durations and therefore cannot adequately represent dynamic project uncertainty.\n  This study presents a Bayesian-Monte Carlo probabilistic schedule updating framework for construction digital twin environments. The proposed methodology integrates stochastic activity-duration modeling, Bayesia"},"verification_status":{"content_addressed":true,"pith_receipt":true,"author_attested":false,"weak_author_claims":0,"strong_author_claims":0,"externally_anchored":false,"storage_verified":false,"citation_signatures":0,"replication_records":0,"graph_snapshot":true,"references_resolved":true,"formal_links_present":true},"canonical_record":{"source":{"id":"2605.17608","kind":"arxiv","version":1},"metadata":{"license":"http://arxiv.org/licenses/nonexclusive-distrib/1.0/","primary_cat":"cs.CE","submitted_at":"2026-05-17T19:09:37Z","cross_cats_sorted":["cs.AI"],"title_canon_sha256":"fe17b02d59dc380f86e377ceaf690f3d0bf38affe6bc0aca2e42e1a086d01b61","abstract_canon_sha256":"7748998f4e3b27fd57ab70b5df95836c0653553344b21e6f73841c51640dc118"},"schema_version":"1.0"},"receipt":{"kind":"pith_receipt","key_id":"pith-v1-2026-05","algorithm":"ed25519","signed_at":"2026-05-20T00:04:48.274166Z","signature_b64":"bexwUUQpyWSfQvD9TwCHxQPjzeRCPUwiBSufly2QL628VuSyimu40y+5EBQ5lq6mNTImLS7o8jQ9Py3nEE8QBQ==","signed_message":"canonical_sha256_bytes","builder_version":"pith-number-builder-2026-05-17-v1","receipt_version":"0.3","canonical_sha256":"9df60c24291961c1079dcbdd35e201cf1f4a4d257215b9c52753d3446c59e7e1","last_reissued_at":"2026-05-20T00:04:48.273310Z","signature_status":"signed_v1","first_computed_at":"2026-05-20T00:04:48.273310Z","public_key_fingerprint":"8d4b5ee74e4693bcd1df2446408b0d54"},"graph_snapshot":{"paper":{"title":"Bayesian-Monte Carlo Schedule Updating for Construction Digital Twins: A Probabilistic Framework for Dynamic Project Forecasting","license":"http://arxiv.org/licenses/nonexclusive-distrib/1.0/","headline":"A Bayesian-Monte Carlo framework updates construction schedules by recursively incorporating new observations to produce adaptive probabilistic forecasts.","cross_cats":["cs.AI"],"primary_cat":"cs.CE","authors_text":"Atena Khoshkonesh, Mohsen Mohammadagha, Navid Ebrahimi, Vinayak Kaushal","submitted_at":"2026-05-17T19:09:37Z","abstract_excerpt":"Construction projects frequently experience schedule delays and forecasting uncertainty due to variability in labor productivity, material availability, weather conditions, and project coordination. Conventional deterministic scheduling methods such as the Critical Path Method (CPM) assume fixed activity durations and therefore cannot adequately represent dynamic project uncertainty.\n  This study presents a Bayesian-Monte Carlo probabilistic schedule updating framework for construction digital twin environments. The proposed methodology integrates stochastic activity-duration modeling, Bayesia"},"claims":{"count":4,"items":[{"kind":"strongest_claim","text":"Simulation experiments using PSPLIB benchmark project networks demonstrate that the proposed framework improves forecasting accuracy and uncertainty representation compared with deterministic CPM and static probabilistic scheduling approaches.","source":"verdict.strongest_claim","status":"machine_extracted","claim_id":"C1","attestation":"unclaimed"},{"kind":"weakest_assumption","text":"Activity durations are adequately represented by lognormal probability distributions and that continuous streams of reliable new observations from BIM, drones, IoT, and logs will be available for Bayesian recursive updating.","source":"verdict.weakest_assumption","status":"machine_extracted","claim_id":"C2","attestation":"unclaimed"},{"kind":"one_line_summary","text":"A Bayesian-Monte Carlo framework for dynamic probabilistic schedule updating in construction digital twins that improves forecasting over deterministic CPM methods.","source":"verdict.one_line_summary","status":"machine_extracted","claim_id":"C3","attestation":"unclaimed"},{"kind":"headline","text":"A Bayesian-Monte Carlo framework updates construction schedules by recursively incorporating new observations to produce adaptive probabilistic forecasts.","source":"verdict.pith_extraction.headline","status":"machine_extracted","claim_id":"C4","attestation":"unclaimed"}],"snapshot_sha256":"d433189dc3a7132a2480d2c13e5782baa51a70640f3e3eaccdb266392521f593"},"source":{"id":"2605.17608","kind":"arxiv","version":1},"verdict":{"id":"473f2429-a330-4e94-8164-9a0c31eda24a","model_set":{"reader":"grok-4.3"},"created_at":"2026-05-19T22:10:27.479538Z","strongest_claim":"Simulation experiments using PSPLIB benchmark project networks demonstrate that the proposed framework improves forecasting accuracy and uncertainty representation compared with deterministic CPM and static probabilistic scheduling approaches.","one_line_summary":"A Bayesian-Monte Carlo framework for dynamic probabilistic schedule updating in construction digital twins that improves forecasting over deterministic CPM methods.","pipeline_version":"pith-pipeline@v0.9.0","weakest_assumption":"Activity durations are adequately represented by lognormal probability distributions and that continuous streams of reliable new observations from BIM, drones, IoT, and logs will be available for Bayesian recursive updating.","pith_extraction_headline":"A Bayesian-Monte Carlo framework updates construction schedules by recursively incorporating new observations to produce adaptive probabilistic forecasts."},"integrity":{"clean":true,"summary":{"advisory":0,"critical":0,"by_detector":{},"informational":0},"endpoint":"/pith/2605.17608/integrity.json","findings":[],"available":true,"detectors_run":[{"name":"cited_work_retraction","ran_at":"2026-05-19T22:53:09.122082Z","status":"completed","version":"1.0.0","findings_count":0},{"name":"doi_title_agreement","ran_at":"2026-05-19T22:31:19.534274Z","status":"completed","version":"1.0.0","findings_count":0},{"name":"doi_compliance","ran_at":"2026-05-19T22:21:36.171925Z","status":"completed","version":"1.0.0","findings_count":0},{"name":"ai_meta_artifact","ran_at":"2026-05-19T21:33:23.570646Z","status":"skipped","version":"1.0.0","findings_count":0},{"name":"claim_evidence","ran_at":"2026-05-19T21:21:57.498826Z","status":"completed","version":"1.0.0","findings_count":0}],"snapshot_sha256":"bbf9eed88c63c3ace317af3ac2147ab37e237bdbce14db10811cf1a51913e409"},"references":{"count":50,"sample":[{"doi":"","year":2012,"title":"P.E.D. Love, D.J. Edwards, Z. Irani, Moving beyond optimism bias and strategic misrepresentation: An explanation for social infrastructure project cost overruns, IEEE Trans. Eng. Manage. 59 (2012) 560","work_id":"11de332a-e9fd-4ec4-bc9d-a6d733cee508","ref_index":1,"cited_arxiv_id":"","is_internal_anchor":false},{"doi":"","year":2014,"title":"Flyvbjerg, What you should know about megaprojects and why: An overview, Proj","work_id":"cdda6667-b84e-475f-a89f-330ae2719601","ref_index":2,"cited_arxiv_id":"","is_internal_anchor":false},{"doi":"","year":2014,"title":"Chitkara, Construction Project Management: Planning, Scheduling and Controlling, McGraw- Hill, 2014","work_id":"88f93e40-c38c-4c60-9a9a-2a9081c3eb81","ref_index":3,"cited_arxiv_id":"","is_internal_anchor":false},{"doi":"","year":2017,"title":"Kerzner, Project Management: A Systems Approach to Planning, Scheduling, and Controlling, Wiley, 2017","work_id":"5220241f-4b97-4644-9f92-d63c1b160593","ref_index":4,"cited_arxiv_id":"","is_internal_anchor":false},{"doi":"","year":1983,"title":"J.J. Moder, C.R. Phillips, E.W. Davis, Project Management with CPM, PERT and Precedence Diagramming, Van Nostrand Reinhold, 1983","work_id":"41d34c49-5038-4b47-8458-41abc93f9d3c","ref_index":5,"cited_arxiv_id":"","is_internal_anchor":false}],"resolved_work":50,"snapshot_sha256":"49ba346b56967980e7cff47265c021ac5d0fff952ab90aa03fa7cf31b9203a7f","internal_anchors":0},"formal_canon":{"evidence_count":2,"snapshot_sha256":"fdbe39d7066a76a6ebb72d9263377a8f6181baea826fc102e16341c81fcd4818"},"author_claims":{"count":0,"strong_count":0,"snapshot_sha256":"258153158e38e3291e3d48162225fcdb2d5a3ed65a07baac614ab91432fd4f57"},"builder_version":"pith-number-builder-2026-05-17-v1"},"aliases":[{"alias_kind":"arxiv","alias_value":"2605.17608","created_at":"2026-05-20T00:04:48.273469+00:00"},{"alias_kind":"arxiv_version","alias_value":"2605.17608v1","created_at":"2026-05-20T00:04:48.273469+00:00"},{"alias_kind":"doi","alias_value":"10.48550/arxiv.2605.17608","created_at":"2026-05-20T00:04:48.273469+00:00"},{"alias_kind":"pith_short_12","alias_value":"TX3AYJBJDFQ4","created_at":"2026-05-20T00:04:48.273469+00:00"},{"alias_kind":"pith_short_16","alias_value":"TX3AYJBJDFQ4CB45","created_at":"2026-05-20T00:04:48.273469+00:00"},{"alias_kind":"pith_short_8","alias_value":"TX3AYJBJ","created_at":"2026-05-20T00:04:48.273469+00:00"}],"events":[],"event_summary":{},"paper_claims":[],"inbound_citations":{"count":0,"internal_anchor_count":0,"sample":[]},"formal_canon":{"evidence_count":2,"sample":[],"anchors":[]},"links":{"html":"https://pith.science/pith/TX3AYJBJDFQ4CB45ZPOTLYQBZ4","json":"https://pith.science/pith/TX3AYJBJDFQ4CB45ZPOTLYQBZ4.json","graph_json":"https://pith.science/api/pith-number/TX3AYJBJDFQ4CB45ZPOTLYQBZ4/graph.json","events_json":"https://pith.science/api/pith-number/TX3AYJBJDFQ4CB45ZPOTLYQBZ4/events.json","paper":"https://pith.science/paper/TX3AYJBJ"},"agent_actions":{"view_html":"https://pith.science/pith/TX3AYJBJDFQ4CB45ZPOTLYQBZ4","download_json":"https://pith.science/pith/TX3AYJBJDFQ4CB45ZPOTLYQBZ4.json","view_paper":"https://pith.science/paper/TX3AYJBJ","resolve_alias":"https://pith.science/api/pith-number/resolve?arxiv=2605.17608&json=true","fetch_graph":"https://pith.science/api/pith-number/TX3AYJBJDFQ4CB45ZPOTLYQBZ4/graph.json","fetch_events":"https://pith.science/api/pith-number/TX3AYJBJDFQ4CB45ZPOTLYQBZ4/events.json","actions":{"anchor_timestamp":"https://pith.science/pith/TX3AYJBJDFQ4CB45ZPOTLYQBZ4/action/timestamp_anchor","attest_storage":"https://pith.science/pith/TX3AYJBJDFQ4CB45ZPOTLYQBZ4/action/storage_attestation","attest_author":"https://pith.science/pith/TX3AYJBJDFQ4CB45ZPOTLYQBZ4/action/author_attestation","sign_citation":"https://pith.science/pith/TX3AYJBJDFQ4CB45ZPOTLYQBZ4/action/citation_signature","submit_replication":"https://pith.science/pith/TX3AYJBJDFQ4CB45ZPOTLYQBZ4/action/replication_record"}},"created_at":"2026-05-20T00:04:48.273469+00:00","updated_at":"2026-05-20T00:04:48.273469+00:00"}